|
Press Release: EPA, April 28, 2004
The United States Environmental Protection
Agency (EPA) today recommended three sites for possible use as sediment
processing/transfer ("dewatering") facilities needed for the
Hudson River PCBs cleanup project.
One or more of these sites will ultimately be selected by late fall of
this year after public comment is received and considered. Three main
operations will occur at these facilities: transferring of dredged sediment
from barges or pipelines to the facility, processing and dewatering of
the sediment, and transferring the processed sediment to barge or rail
for off-site disposal. The facilities will be constructed using proven
technology to ensure that dredged material is handled safely.
EPA evaluated seven final candidate sites that were identified in September
2003. Based on these evaluations, five sites were found to be suitable
for use as dewatering facilities. Suitable sites are those that met the
engineering criteria and environmental characteristics needed for a dewatering
facility. Of the five suitable sites, three sites are being recommended,
and two sites are being retained for possible consideration in the future
although EPA considers their use unlikely. Two of the seven final candidate
sites have been eliminated by EPA from further consideration.
Recommended Sites
| Energy Park/Longe/New York State Canal Corporation |
Ft. Edward, Washington County |
| Bruno/Brickyard Associates/Alonzo |
Schaghticoke, Rensselaer County |
| OG Real Estate |
Bethlehem, Albany County |
Sites Being Retained as Suitable, But Not Recommended at this Time
| Old Moreau Dredge Spoils Area |
Moreau, Saratoga County |
| New York State Canal Corporation/Allco/Leyerle |
Halfmoon, Saratoga County |
Eliminated Sites
| Georgia Pacific |
Greenwich, Washington County |
| State of New York/First Rensselaer/Marine Management |
Rensselaer, Rensselaer County |
In December 2002, EPA began the facility site selection process by focusing
on industrial and/or commercial properties within a half-mile of the river
between the Hudson Falls Dam and the area just below the Port of Albany.
Locations within this area were evaluated using three groups of criteria
provided to the public in the Hudson River PCBs Site Facility Siting Concept
Document. In June 2003, EPA provided a public update on the facility siting
process that identified 24 preliminary candidate sites retained for site-specific
investigations. This was followed by a September 2003 update that identified
seven final candidate sites that would undergo a detailed evaluation.
Each of the seven final candidate sites was evaluated using engineering
criteria (sufficient space for facility construction and operations; river,
road and rail access; availability of utilities; and proximity to the
areas that will be dredged) and additional criteria (sensitive or cultural
resources, existing and historic land uses, rare or unique ecological
communities, threatened and endangered species, ease of purchasing/land
ownership, wetlands, geology or surface features, and mapped 100-year
flood plain or floodway data). A final set of criteria was added to identify
the suitable and recommended sites. The critiera included key design and
logistical considerations such as usable space, rail yard and waterfront
suitability, site characteristics and conditions, road access, and river
navigation.
EPA eliminated the Georgia Pacific site based on factors that included
limited working rail access and the presence of significant cultural resources
that would present construction difficulties and would limit the amount
of useable space needed for the facility. EPA eliminated the First Rensselaer
site because of insufficient useable space, potential flooding, and lack
of a residential buffer area.
EPA is continuing its expanded outreach program and will work diligently
with communities during final selection of the dewatering facility sites.
A public comment period on the Draft Facility Siting Report is being held
from May 3 through July 1, 2004. The Draft
Facility Siting Report is available on the project Web site at www.epa.gov/hudson
and at information repositories located in Glens Falls, Ft. Edward, Ballston
Spa, Albany, Poughkeepsie, New York City and Edgewater, New Jersey. Copies
are also available on CD-ROM by calling the Hudson
River Field Office.
EPA will host public forums during the public comment
period, one forum in each of the communities in which a suitable site
has been identified. The public forums will be held on:
|
Site
|
Meeting Day
|
Date
|
Time
|
Meeting Location
|
Energy Park/Longe/NYSCC
Ft. Edward
Washington County |
Tuesday |
5/11/04 |
6:00 to 8:30 PM |
Ft. Edward Fire Hall 116 Broadway
Ft. Edward, NY
|
Bruno/Brickyard Assoc./ Alonzo
Schaghticoke
Rensselaer County |
Wednesday |
5/12/04 |
6:00 to 8:30 PM
|
Stillwater Community Center
19 Palmer Street
Stillwater, NY |
OG Real Estate
Bethlehem
Albany County |
Thursday |
5/13/04 |
6:00 to 8:30 PM |
Delmar Reformed Church
386 Deleware Ave.
Delmar, NY
|
Old Moreau Dredge Spoils Area
Moreau
Saratoga County |
Tuesday |
5/18/04 |
6:00 to 8:30 PM |
Moreau Community Center
144 Main Street
South Glens Falls, NY
|
NYSCC/Allco/Leyerle
Halfmoon
Saratoga County |
Wednesday |
5/19/04 |
6:00 to 8:30 PM |
Clifton Park Elks #2466
695 MacElroy Road
Clifton Park, NY
|
|